Before they start powering servers up, some testing has to happen and the temps have to stabilize. Cooling has to be done in a controlled manner, otherwise we run into possible condensation issues.
Generally, when powering servers up, it has to be done in steps. The amperage peaks during the boot process, so we don't want to do it all at once or we risk taking a large part or all of the phase back offline.
I know you guys are frustrated, as are we, and I appreciate the patience. Hopefully, we, you guys, and the industry can learn from this incident.
Tomy Durden
Data Center Manager -- Dllstx2 / Dllstx6
Monday, June 2, 2008
The Planet - H1 Phase 2 Power Up In Progress
Tomy Durden explains why it takes time to power up.
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment