The Planet - H1 Phase 2 Racks Power On In Progress

My server will be up anytime from now, hopefully latest by 23:59 2nd June 2008 Singapore time.

Today, 01:55 AM

Following the restoration of power to the second floor of the data center, we've cooled the data center floor and are now in the process of systematically restoring power to racks.

We've got a full staff in the data center to power up racks in sections and verify that the server hardware starts up successfully. This process may take a few hours to restore service to all customer servers on the second floor.